Reports / Projects / DON TOLIVER / AUG 2026
450 Don Toliver "Octane" Grammy FYC boxes — vinyl, RC car, booklet, and a component list that doubled overnight — requested, escalated, scoped, and executed inside a ~30-hour window under a hard noon deadline to Sherman Oaks. Documented from the email record; execution-day details pending confirmation and marked accordingly.
Requested at 12:18 AM for same-day completion: build and collate 450 Grammy boxes, three components, finish by EOD. By 8:44 PM the spec had grown to six components across four locations, none of the boxes had arrived (vendor production delays), and the deadline had hardened to noon 8/26 delivery in Sherman Oaks. TITOL declared it priority over all other work. The job was scoped honestly at 1 AM, executed 8/26–27, and invoiced $6,130 on 8/28.
// Destination: ATTN Leslie Lewis, 13352 Valley Vista Blvd, Sherman Oaks, CA 91423 (Dianne arranging pickup). Requested by Martin; escalated by Carla with Jesse, Dianne, Shayne, Naja, Reider, V, and Adelaida looped in. Every timestamp below is from the thread record.
Carla's 8:44 PM "rapid fire" list, as stated. Only one of six components was on-site the night before the noon deadline. Two component quantities were below the 450 target as communicated.
| # | Component | Qty stated | Location night before | Stated ETA (8/26 AM) | Note |
|---|---|---|---|---|---|
| 1 | Vinyl | — | ✓ Already at warehouse | On hand | Only component in place |
| 2 | RC Cars | 269 | TITOL offices | 8:30 AM | 181 short of 450 — caps complete builds unless more arrive |
| 3 | Hats | 200 | Products Go (exit placed) | 8:30–10 AM | 250 short of 450 — partial-inclusion assumed, TBC |
| 4 | Brochures | — | At vendor | 8–9 AM | Pickup + drop-off same morning |
| 5 | Boxes | — | At vendor (production delayed) | Pending | 4-part build each — the late-discovered feasibility killer; corrugated shippers sourced separately by TITOL/VT via ULINE will-call (500 ct, 7 AM) |
| 6 | Cards | — | Printing overnight | Pending | ETA never firmed in thread |
// Box spec: 15 × 15 × 4.5 in, square (no staggered stacking). The original 12:18 AM ask listed only vinyl + RC car + booklet; hats, cards, and the 4-part box build surfaced later — the scope change that reshaped feasibility.
From first ask to feasibility memo in 25 hours; invoice out on day four.
What the warehouse controlled, it handled the same night; what it couldn't control, it escalated in writing with options instead of objections.
// This sprint is the documented case study for the Weekly Project Management proposal sent to Carla on 8/8: a work order landing with <24h notice, components across four locations, and scope doubling mid-flight — handled with postponement discipline, written feasibility math, and options-first escalation.
The thread goes quiet after the 1 AM memo; the invoice proves the job ran. Fill in the confirmed numbers and the ledger computes completion against target and the component cap.
// Component cap = min(cars, boxes built) — vinyl was on hand; hats (200) assumed partial-inclusion, not a cap, until confirmed otherwise. Zeros mean "not yet confirmed," not zero production.
// Invoice reference: $6,130 · "OCTANE GRAMMY BOX COLLATION" · sent 8/28 to naja@, dianne@, finance@, carla@ · Zelle preferred.
The job is billed; the record needs four confirmations to close.